FORT BRAGG (FAYETTEVILLE, NC)
This project consisted of the removal and abatement of ACM and universal wastes followed by the demolition of approximately 660,000 square feet of structures including 13-3 story barracks constructed of concrete and block. Trinity Industrial Services recycled approximately 75% of the former building materials for beneficial reuse, which qualified for a successful LEEDS “Silver Project.” The project was completed in 180 days at a project cost of $2,425,000.
Project Reference: Martin Munoz, United States Army Corp of Engineers and Wade Jones, Archer Western